In our planning system, there are provisions that potentially allow unauthorised development to become lawful after a specific period of time. The principle being that if no one has noticed or had concerns about a development, even if it doesn’t have consent, it should be allowed to continue.

Depending on the circumstances, there are two relevant periods that apply, 4 years or 10 years.

The 4 year rule applies to any ‘operational development’, such as building, engineering, mining or other operations. The 4 year rule also applies to a change in the use of a building to a single dwelling house.

For any other breach of planning control, a 10 year rule applies. This would therefore apply to other changes of use and breaches of planning conditions.

Where a breach of planning has been taking place in excess of the relevant period, it is often sensible to regularise this with the planning authority by applying for a certificate of lawful existing use. This involves the submission of sufficient evidence to prove that the breach has been in place, uninterrupted, for enough time. It is often easier to do this proactively, rather than having to fight against an enforcement notice.

It’s worth noting that the Levelling Up and Regeneration Bill, which was introduced into Parliament in May 2022, seeks to amend these time periods. If passed, the Bill will extend the enforcement period to 10 years in all cases. It therefore might be sensible to get certificates of lawfulness for any 4 year breaches now, before the period ends up being 10 years.

Regularising planning anomalies can also add significant value to a property and potentially avoid problems when a property is being sold. If you are thinking of selling at some point in the future, sorting these things out in good time is a very worthwhile exercise.